This shows the onsite fabrication and installation of two atomiser silos to a biomass power station build. The first stage was the fabrication and installation of the support rings. The second stage was the fabrication of the cone sections. Both cone sections were constructed inverted and then topped and tailed for final installation. The third stage was the fabrication and installation of the roof and walls for each silo. The build method required that the roof was constructed first with each new course of wall panels being added underneath.
The final lift was a load of 31.5Te (net) going to a radius of 42m